TANJUNG ENIM PSC

Awarded on 3 August 2009 (30 Years Contract)

Contractors :
Dart Energy (Tanjung Enim) Pte Ltd (1) 45% (Operator)
PT Pertamina Hulu Energi Metra Enim (2) 27.5%
PT Bukit Asam Metana Enim (3) 27.5%
Current Acreage: 249.10 km2
Reserves: (4)
  • Gas In Place
484 BCF
  • P1 / P2 / 2P
113 / 102 / 215 BCF
  • Recoverable Reserve
165 BCF (from 33 km2 out of 249.1 km2) / POD-1
Exploration Data:
  • CBM Wells (drilled by NuEnergy Gas)
13 wells
  • Coal mining core holes
27 wells
  • Seismic lines
55 lines
  • Conventional oil and gas wells
5 wells
Strategic Location:
  • Located about 50 km and 130 km from growing economy and industrial cities of Prabumulih and Palembang respectively
  • Well developed infrastructure with long establishment of Bukit Asam Coal Miner and Pertamina Oil and Gas Facilities
  • About 35 km from major gas trunk lines to Java market and export to Malaysia and Singapore
Current Status:
  • POD1 approved by the Ministry of Energy and Mineral Resources ("MEMR") on 17th June 2021, for development of gas production to a plateau of up to 25MMSCFD.
  • MEMR has approved a gas allocation on 29 August 2025 for the sale of 1MMSCFD of CBM and GSPA signed with PT Perusahaan Gas Negara Tbk (“PGN”).
  • Under early gas sales initiative, 4 planned wells were completed, with thicker overall coal seams than prognosed and dewatering is progressing well.
TE-B06-001
TE-B06-002
TE-B06-003
TE-B01-003

Notes:

(1) Subsidiary of NuEnergy Gas Limited
(2) Subsidiary of PT Pertamina (State Owned Oil and Gas Company)
(3) Subsidiary of PT Bukit Asam (State Owned Coal Mining Company)
(4) The resources estimates were certified by Netherland Sewell & Associates Inc, November 2012 and reported at net of NuEnergy Gas working interest. Gas in place estimate was reported at gross.